By
Thomas Krause

Start of production on time

The slabline plant was brought into operation as scheduled and handed over in Tatarstan / Russia at the 01. July 2018. Due to keeping all contractual specificatins the final take over certificate was already issued one week later. Bromkamp was turn-key supplier incl. CE certification for the machine equipment. Big appreciation to the entire team for the good performance taking…



By
Thomas Krause

Bromkamp equips a curing oven

Bromkamp receives the order for the complete mechanical and electrical equipment of the curing furnace for a new plant in the mineral wool industry in the USA. The scope of supply including post-combustion has an installed thermal capacity of 8.5 MW.